Geotechnics and Geometallurgy · August 2024
Validating Strength and Hardness on 550 m of Half Core
MPT half-core and lump tests on about 550 m of core from a VMS deposit, compared with point load and SMC drop weight tests.
- Project
- VMS deposit
- Location
- Confidential
- Application
- Geotechnical and geometallurgical characterization
- Samples
- Half core and lump samples
- Compared against
- Point load, SMC drop weight (A×b, DWi)
PaperAdvancing Orebody Knowledge with High-Resolution Rock Strength Measurement Using the Minpraxis Tester · Procemin-GEOMET 2024, Santiago
Read the paperContext
About 550 m of half core from a volcanogenic massive sulfide (VMS) deposit was used to validate the MPT for geotechnical and comminution characterization.
The Work
The core was grouped into 51 composites of about 11 m, each with 20 half-core point load tests, and the half core was tested on the MPT. The MPT product was then sieved, and one size fraction went to SMC drop weight tests and MPT lump tests.
Results
MPT predictions of point load strength (IS50) agreed with the measured values within 15%, and half-core predictions of DWi and A×b also fell within 15%. MPT lump tests, which take less than an hour, came within 10% for DWi and 15% for A×b.


